EAST STAND UPDATE, 19 MAY 2015

19 May 2015

Latest pictures and information from the East Stand

Work is continuing to progress well on the East Stand.

WORK RECENTLY COMPLETED/IN PROGRESS
Drainage work completed
Brickwork progressing well around ground floor

WORK TO TAKE PLACE IN NEXT FEW DAYS
Second floor to be concreted on Wednesday May 20th
First floor to be concreted on Wednesday May 27th
Brickwork to continue